Biodegma: MSW treatment in Kepno

The MSW treatment in Kepno has successfully passed the final test run and has been accepted by the final client ZZO Olszowa. The plant is stabilizing 17,250 t/year of MSW fraction 0/80mm. 6 BIODEGMA tunnels have been installed for the intensive stage composting. After the overall treatment process including the maturation stage the material has an AT4 <10 mg O2/kg TS and is landfilled. An overview of the site is available on http://www.zzo-olszowa.pl/index.php/filmy